Status: Draft Basic Assessment Report and Appendices
- Reference Number: S24G/03/25-26/0708
- Authority: Gauteng Department of Environment (GDEnv)
- Date of notice: 2026-04-02
- Closing date: 2026-05-06
BACKGROUND
The Applicant, Victoria Bricks (Gauteng) (Pty) Ltd, is submitting an application for authorisation in terms of Section 24(G) for the unlawful construction and operation of a rotary kiln.
LEGISLATIVE PROCESS
Victoria Bricks has triggered activities published under the Environmental Impact Assessment (EIA) Regulations, 2014 (GNR982 of 2014, as amended) and Listing Notices. The following activities have been triggered:
Listing Notice 2 (GNR 984 of 2014, as amended)
- Activity 6: The development of facilities or infrastructure for any process or activity which requires a permit or licence or an amended permit or licence in terms of national or provincial legislation governing the generation or release of emissions, pollution or effluent.
PUBLIC PARTICIPATION PROCESS
The purpose of the Public Participation Process (PPP) is to notify Interested and Affected Parties (I&APs) of the proposed project and to provide them with the opportunity to raise issues or concerns regarding the project.
As part of the PPP, the identified I&APs, stakeholders and the public are provided with a 30-day period from 2 April 2026 until 6 May 2026 to register as an I&AP and participate in the PPP.